Whole-house brick & block estimator with room-by-room design, window/door deductions, UAE/Pakistan/India brick standards, mortar, concrete, tiles, paint, steel & more.
Pick any calculator below. UAE, Pakistan & India standards pre-loaded.
Gross Area = L × H
Opening Area = (nDoors×dW×dH) + (nWins×wW×wH) + (nGates×gW×gH)
Net Volume = (Gross Area − Opening Area) × Wall Thickness
Brick Module Vol = (bL+joint) × (bH+joint) × (bW+joint)
Net Bricks = ceil(Net Volume ÷ Brick Module Vol)
Purchase = ceil(Net Bricks × (1 + Wastage%))
Mortar vol estimated as total vol minus net brick solid volume.
Opening Area = (nDoors×doorArea) + (nWins×winArea) + extraOpenings
Net Area = (L×H) − Total Opening Area
Block Face = (BlockL+Joint) × (BlockH+Joint)
Net Blocks = ceil(Net Area ÷ Block Face)
Purchase = ceil(Net Blocks × (1 + Wastage%))
Dry Volume = Wet Volume × 1.33
Cement Vol = (C/(C+S)) × Dry Vol × (1+wastage)
Cement Weight = Cement Vol × 1440 kg/m³
Bags = ceil(Cement Weight ÷ Bag Size)
Sand Vol = (S/(C+S)) × Dry Vol × (1+wastage)
Factor 1.33 accounts for reduction in volume when dry materials fill wet space.
Volume = L × W × D × Qty
Purchase Vol = Volume × (1 + Wastage%)
Dry Volume = Purchase × 1.54
Cement = (C/Total) × Dry Vol × 1440 kg/m³
Densities: Cement 1440 | Sand 1450 | Aggregate 1500 kg/m³
Net Area = (L×H) − Openings
Wet Volume = Net Area × Thickness
Dry Volume = Wet Vol × 1.27
Cement = (1/(1+Ratio)) × Dry Vol × (1+wastage) × 1440
Sand = (Ratio/(1+Ratio)) × Dry Vol × (1+wastage)
Net Area = (L×W) − Deductions
Purchase Area = Net Area × (1 + Wastage%)
Tiles = ceil(Purchase Area ÷ Tile Area)
Boxes = ceil(Tiles ÷ Tiles per Box)
Unit Weight (kg/m) = D² ÷ 162.28
Net Length = Bar Length × No. of Bars
Total Length = Net Length × (1 + Wastage%)
Total Weight = Total Length × Unit Weight
D = diameter in mm. Formula from steel density 7850 kg/m³.
Questions? Need help with a project? WhatsApp us directly.